Can I Swim by Memorial Day? Month-by-Month Timeline for Chicagoland Builds
If you’re planning a new inground pool in the Chicago suburbs, you’ve probably asked the big question: Can we be swimming by Memorial Day? It’s a classic Midwest milestone—school’s almost out, the patio furniture is back, and everyone’s ready to live outside again.
Here’s the clear answer most homeowners want:
Yes—your pool can be ready by Memorial Day, but only if you start far earlier than most people expect. In Chicagoland, the biggest limiter isn’t always construction—it’s plans + engineering + permits, which can take months. To truly ensure you have a realistic shot at swimming by Memorial Day, you should plan to sign a contract between July and October of the prior year.
That early commitment gives enough runway to complete design and engineering, move through permitting, and reserve a build window that can start in January through March. That winter-start capability is something Sunset Pools & Spas can offer—and it’s one reason our customers can get ahead of the spring rush when many builders are still waiting for weather or permits.
Bottom Line Up Front: What It Takes to Be Swimming by Memorial Day
- To have the best chance of a Memorial Day swim: sign a contract July–October (prior year).
- Why so early? Plans, engineering, and permits can take several months—and permits are often what hold projects up.
- Construction timing: Sunset Pools can begin construction in January–March (weather and site conditions permitting), which is earlier than most pool companies in the region.
- If construction starts in April: a common expectation is June completion (after Memorial Day).
Why Permits Control the Pool Construction Timeline in Chicago
In Chicagoland, permit timelines vary greatly by municipality. Some towns are relatively quick, while others take multiple review cycles and can stretch out for months. That’s why even a “fast build” can’t move forward until approvals are secured.
In other words: if Memorial Day is the goal, you need a timeline that protects you from permit uncertainty by starting early—well before winter turns to spring.
Two Paths: Memorial Day Target vs. Typical Spring Start
Path A: The Memorial Day Target (Earlier Than Most People Think)
If Memorial Day is your priority, the schedule below is the most realistic approach:
- Contract signed: July–October (prior year)
- Design + engineering: late summer through fall
- Permits: fall into winter (timing varies by municipality)
- Construction start: January–March (when site conditions allow)
- Goal: finishes and startup completed in time for Memorial Day
This is where Sunset Pools stands out: we can begin construction in the winter months (January–March), which helps homeowners reach earlier swim targets that many builders simply can’t accommodate.
Path B: The Typical Chicagoland Timeline (April Start → June Completion)
Many homeowners begin planning too late for Memorial Day—and that’s why the “standard” expectation looks like this:
- Contract signed: November-December (prior year)
- Design + engineering: late fall into winter
- Permits: winter through early spring
- Construction start (excavation): April
- Completion: commonly June (depending on weather, inspections, decking, and finishes)
This is a great outcome for most families—but it’s after Memorial Day.
Month-by-Month Timeline: Memorial Day Planning (Best-Case Roadmap)
If you want a strong shot at being ready by Memorial Day, this is the planning cadence to follow:
| Month | Primary Focus | What You Should Be Doing | Why It Matters |
|---|---|---|---|
| July–October (prior year) | Contract + kickoff | Reserve your build window, start site review, confirm goals/features, gather survey | Getting “in the queue” early protects your Memorial Day target |
| October–December | Design + engineering | Finalize pool layout, depth, features, equipment plan, and engineering requirements | Plans must be complete before permits can move efficiently |
| November–January | Permit submission + reviews | Submit permits, handle revisions, coordinate utility locates and municipality requirements | Permits can take several months and are the most common source of delays |
| January–March | Construction start window (Sunset capability) | Begin construction as weather and site conditions allow; start early phases and scheduling | Starting earlier than most builders creates the best Memorial Day opportunity |
| March–May | Finishes + startup | Tile/coping, decking, interior finish, fill, startup, final inspections and walkthrough | May should be “startup ready,” not “still building the shell” |

What If My Town Has Faster Permits?
There are exceptions. Some municipalities (often farther from the metro core) can have shorter permit processes. In those cases, you might be able to compress the schedule.
But if your goal is to ensure a Memorial Day-ready pool—and not just “hope for it”—the safest strategy remains: sign by July–October of the prior year. That schedule is designed to handle real-world permit variability without derailing your swim deadline.
How to Keep Your Memorial Day Target on Track
Even with early planning, schedules can slip if decisions or approvals stall. The best ways to protect your timeline include:
- Choose finishes early: tile, coping, decking approach, lighting, and automation.
- Limit late changes: revisions after permit submission can restart review cycles.
- Plan access and staging: fencing, gates, and backyard access affect schedule.
- Expect weather buffers: Chicagoland winter and spring conditions require flexibility.
So, Can You Swim by Memorial Day in Chicagoland?
Yes—if you plan early enough. If you want the best chance to be ready by Memorial Day, plan to sign a contract between July and October of the prior year so your design, engineering, and permits can be completed in time. Because permits often take several months, they’re usually the factor that determines whether the project can begin early enough.
If you don’t start until an April construction window, a more typical expectation is June completion—which is still a great outcome, just after Memorial Day.
Ready to Get in the Queue for a Memorial Day Swim?
Sunset Pools & Spas is family-owned and operated, with 17+ years of experience building custom concrete inground pools across Chicagoland. We manage the entire process—design, engineering, permits, construction, and startup—with the planning discipline needed for homeowners targeting an early swim season.
Contact Sunset Pools & Spas to review your property and municipality requirements and to map out a personalized schedule for your Memorial Day goal.
Pool Construction Timeline Chicago FAQs
Can a new pool really be ready by Memorial Day in Chicagoland?
Yes, but it requires early planning. To best ensure a Memorial Day-ready pool, homeowners should typically sign a contract between July and October of the prior year so design, engineering, and permits can be completed in time to start construction early.
When should I sign a contract if I want to swim by Memorial Day?
For the best chance, plan to sign between July and October of the prior year. This allows time for plans, engineering, and a permit process that can take several months.
Why do permits affect the pool construction timeline in Chicago so much?
Permit timelines vary greatly by municipality and often involve review cycles and revisions. Because construction can’t begin until approvals are secured, permits are one of the most common causes of schedule delays—especially for homeowners targeting early swim dates.
Can pool construction really start in the winter months?
In some cases, yes. Sunset Pools can begin construction in the January–March window when weather and site conditions allow, which is earlier than many pool companies and can improve the odds of being ready by Memorial Day.
If construction starts in April, when is the pool usually finished?
An April start often targets a June completion in Chicagoland, though exact timing depends on weather, inspections, and the scope of decking and finishes.